name: cvpr-workflow
description: Use when planning a CVPR submission campaign end to end, covering the November abstract/paper/supplement deadline chain, coauthor reviewer-duty scheduling, the January rebuttal sprint, February decisions, camera-ready and June conference logistics, and the resubmission ladder across ICCV, ECCV, and the next CVPR.
---

# CVPR Workflow

CVPR is an annual machine with one intake: in the 2026 cycle, abstracts November 6,
papers November 13, supplements November 20, rebuttal late January, decisions
February 20, conference June 3–7 in Denver. This skill turns that spine into a
project plan with owners, because CVPR deadline weeks are lost to coordination
failures more often than to science failures.

## Campaign calendar (2026-cycle anchors)

| When | Milestone | Owner discipline |
|---|---|---|
| T–10 weeks (early Sep) | Freeze scope: claims, benchmarks, baselines | PI + first author sign one paragraph |
| T–8 weeks | Experiment matrix running; recipe ledger live | Every table row has a config |
| T–6 weeks | First full draft; flip-test the figures | Co-authors annotate, don't rewrite |
| T–4 weeks (early Oct) | OpenReview profiles audited for every author | One named owner; new coauthors close the list |
| T–1 week (Nov 6) | **Abstract registered; profiles valid** | Desk-reject exposure if missed |
| Nov 13 | **Paper + CRF submitted** | Freeze 24h early; upload before the panic hour |
| Nov 20 | **Supplement uploaded** | Videos/code packaged per `cvpr-supplementary` |
| Dec – Jan 12 | Coauthors deliver their assigned reviews | Late reviews endanger *your* paper |
| Jan 22–29 | Reviews land; one-page rebuttal | Pre-book this week; nobody travels |
| Jan 30 – Feb 5 | Discussion (no author access) | Resist mailing the AC |
| Feb 20 | Decisions | Both branches pre-planned |
| Spring (待核实) | Camera-ready + dataset release due | See `cvpr-camera-ready` |
| Jun 3–7 | Conference (workshops 3–4, main 5–7 in 2026) | Poster/talk/travel logistics |

## The two windows people fail to defend

**Deadline fortnight (early November).** The supplement trailing the paper by a week
tempts teams to leave packaging "for week two" — then week two evaporates into video
rendering and code scrubbing. Rule: the supplement plan (what goes in, who builds it)
is written *before* the paper deadline; week two only executes it.

**Rebuttal week (late January).** Seven days, one page, all reviewers at once. Assign
roles when reviews drop, not after a day of group grief:

```yaml
# rebuttal-roles.yaml — filled within 12 hours of review release
reader:        # summarizes all reviews neutrally, one page, no rebuttals yet
runner:        # owns the 1-2 small requested experiments; hard stop at day 5
writer:        # owns the single page; everyone else feeds bullets
adjudicator:   # PI decides which objections get space, which get one line
deadline:      # internal freeze 24h before OpenReview close
```

## Reviewer duty as a planned workload

Submitting enrolls qualifying authors into a 25k-reviewer pool, and undelivered or
irresponsible reviews can desk-reject every paper the offender authored (verified 2026
enforcement). Treat December–January reviewing as a scheduled deliverable: at
submission time, list which coauthors are likely reviewers, block their calendar for
review weeks, and have the group's senior authors sanity-check first-time reviewers'
drafts against the official reviewer guidelines.

## Multi-paper coordination

Most labs submit several papers into the same November wall, which multiplies the
process risks nonlinearly:

- **Shared coauthors, shared exposure**: one person's undelivered January review
  endangers every paper they touch; the duty ledger must be lab-level, not
  paper-level.
- **Conflict hygiene**: OpenReview conflicts must be complete across all submissions;
  a stale institution on one profile pollutes assignments for the whole batch.
- **Compute contention**: rebuttal-week reserve GPU allocations collide when three
  papers each promised "small requested experiments"; pre-negotiate priority order.
- **Internal review**: schedule lab-mates' cross-reads at T–10, not T–2 — at T–2
  everyone is defending their own draft.

## The resubmission ladder

At a 25.42% acceptance rate, the rational plan covers rejection before it happens. The
CV calendar offers a clean ladder — CVPR (Nov) → ICCV (spring deadline, odd years) /
ECCV (spring deadline, even years) → WACV/3DV or back to CVPR. Rules for climbing:

- Bank the reviews: fix every factual objection before the next deadline; reviewer
  pools overlap across CVF venues and repeat objections read badly (triage method in
  `cvpr-review-process`).
- Mind the dual-submission windows: the CVPR attestation covered Nov 13 – Feb 20 in
  2026; the next venue's window must not overlap a paper still under CVPR review.
- Re-check freshness: three months of arXiv can obsolete a comparison table; budget a
  baseline-refresh pass, not just an edit pass.

## Deadline fortnight, day by day

The last two weeks compress badly when run ad hoc. A schedule that has survived
contact with real teams:

- **T–14 to T–10**: results freeze for the main table. New numbers after this go to
  the supplement or the rebuttal, not the body.
- **T–10 to T–7**: full-draft pass; run the figure flip test with an outsider; final
  baseline-freshness check against the leaderboard.
- **T–7 (abstract day)**: register the abstract, verify every profile renders as
  complete when logged out of the authors' accounts, lock the author list.
- **T–6 to T–3**: claim-calibration pass (`cvpr-writing-style`), bibliography venue
  verification (`cvpr-related-work`), CRF mandatory sections drafted.
- **T–2**: full mechanical sweep from `cvpr-submission`; internal freeze.
- **T–1**: upload; re-download; cold read. Nobody edits after upload day.
- **T to T+7 (supplement week)**: execute — do not design — the supplement plan;
  identity-scan code and videos; upload at T+5, not T+7, to survive a failed render.

## Cycle-status note

As of 2026-07-08, CVPR 2026 has concluded and the CVPR 2027 cycle (Seattle, reported
around June 20–24, 2027) had published **no** CFP or deadlines. Every date above is a
2026-cycle anchor for planning shape only — reopen cvpr.thecvf.com the moment your team
commits, because the deadline chain (and things like the CRF) can change between
editions.

## Output format

```text
[Campaign stage] scoping / building / deadline-fortnight / in-review / rebuttal / decided
[Calendar] next 3 milestones with dates and owners
[Duty ledger] reviewing coauthors + calendar blocked: yes/no
[Risk register] top 3 (missed-profile, supplement drift, rebuttal roles, …)
[Plan B] next venue + its verified deadline
[Cycle check] current-year pages reopened on: <date>
```