name: implementation-task-plan
description: Generate an implementation task plan from design documents. Breaks a low-level design into ordered, dependency-aware tasks with explicit parallelization analysis. Use when you have a completed low-level design and need to plan the implementation work.
argument-hint: "[prefix] [output path, or leave blank for plan/{prefix}-plan.md]"
---

Generate a task plan that breaks a low-level design into implementable units with precise dependency and parallelization analysis.

This is not a simple list of things to build. The plan must answer:
- **What depends on what?** (hard prerequisites)
- **What can truly run in parallel?** (independent packages, no shared files)
- **What has no ordering dependency but can't be done simultaneously?** (same package, shared tests, merge conflict risk)

## Input

The user may provide: $ARGUMENTS (prefix, custom output path, or constraints on task granularity)

## Expected Folder Structure

```
project/
├── design/
│   ├── {prefix}-requirements.md          # Reference: for traceability
│   ├── {prefix}-high-level-design.md     # Reference: for component context
│   └── {prefix}-low-level-design.md      # Primary input: drives the task breakdown
├── plan/
│   └── {prefix}-plan.md                  # Output: task plan (includes task status tracking)
```

## Process

### Phase 1: Locate and Read Documents

1. **Determine the design prefix:**
   - If $ARGUMENTS provides a prefix (first word that is not a file path), look for `design/{prefix}-low-level-design.md`, `design/{prefix}-requirements.md`, and `design/{prefix}-high-level-design.md`
   - If no prefix is provided, scan `design/` for files matching `*-low-level-design.md` (this is the primary input)
     - **One match:** Use it and infer the prefix from the filename (e.g., `foo-low-level-design.md` → prefix is `foo`)
     - **Multiple matches:** Use AskUserQuestion listing the discovered files and ask the user which design to plan
     - **No matches:** Also check for an unprefixed `low-level-design.md`. If found, use it with no prefix. Otherwise, use AskUserQuestion to ask the user where to find the low-level design
   - Once the prefix is established from the low-level design file, use the same prefix to locate the requirements and high-level design files
   - If no prefix can be determined, ask the user

2. **Look for low-level design** at `design/{prefix}-low-level-design.md` — this is the primary input
3. **Look for requirements** at `design/{prefix}-requirements.md`
4. **Look for high-level design** at `design/{prefix}-high-level-design.md`
5. **If any are missing:** Use AskUserQuestion to ask the user where to find them. The low-level design is required. Requirements and high-level design are strongly recommended.

Read all documents thoroughly. The low-level design is the primary source for task breakdown. The requirements provide traceability targets. The high-level design provides component context.

### Phase 2: Identify the Parallelization Topology

Before breaking tasks down, map the structural boundaries that determine what can run in parallel. Extract from the low-level design:

1. **Package/module boundaries** — Each distinct package is a potential parallelization unit. Tasks within the same package touch shared files (test files, module declarations, re-exports) and will conflict if done concurrently.

2. **Cross-package dependencies** — The package dependency graph from the low-level design tells you which packages must exist before others can be built.

3. **Shared infrastructure** — Some things are used by everything: error types, configuration, shared utilities, test helpers. These must come first.

Build a mental model of the workspace:
```
workspace/
├── pkg-a/         ← depends on: pkg-core
├── pkg-b/         ← depends on: pkg-core, pkg-a
├── pkg-c/         ← depends on: pkg-core
├── pkg-core/      ← depends on: nothing
└── test-helpers/  ← depends on: pkg-core
```

In this example:
- `pkg-a` and `pkg-c` can be built **truly in parallel** (different packages, no shared files)
- Two tasks within `pkg-a` are **order-independent but not parallel** (they'll edit the same test files, same module declarations)
- `pkg-b` must wait for both `pkg-a` and `pkg-core` (**sequential dependency**)

### Phase 3: Break Down Tasks

Walk through each package/module from the low-level design and create tasks for:

**Per package, typically in this order:**

1. **Package scaffolding** — Create the package, set up module structure, add to workspace
2. **Core types** — Structs, enums, traits/interfaces defined in the class diagrams
3. **Trait/interface implementations** — One task per significant implementation
4. **Internal logic** — Private helpers, algorithms, state machines
5. **Unit tests** — Tests for the classes in this package (reference the testing strategy from the low-level design and the requirement IDs they cover)

**Cross-cutting tasks:**

6. **Integration points** — Where packages wire together (these depend on both packages being complete)
7. **Integration tests** — End-to-end tests from the testing strategy (reference requirement IDs)
8. **Configuration & wiring** — Startup sequence, dependency injection, main entry point

**Task sizing rules — the context window test:**

The goal is that each task can be completed by a coding agent in a single context window. That means the agent needs to read the relevant existing code, understand the task, write the implementation, and verify it — all without running out of context. Use these guidelines:

- **One file is the ideal unit.** A task that creates or modifies a single file is almost always the right size.
- **Tightly coupled files are okay** — e.g., a struct and its unit test file, or a trait definition and its one impl. But keep it to 2-3 files max, and only when they genuinely can't be split.
- **Each file should not be individually complex.** If a single file involves a large state machine, complex algorithm, AND extensive error handling, that's probably two tasks even though it's one file.
- **The agent must be able to hold the full picture.** If completing the task requires reading more than ~5-6 existing files for context, the task is scoped too broadly.
- **A task must be verifiable on its own** — it should compile and its tests should pass with only prerequisite tasks complete.
- **If a task touches more than one package, it's almost certainly too big** — split it.

**Splitting heuristics — when in doubt, split:**
- A struct with many methods → one task for the struct + core methods, another for secondary methods
- A trait with multiple implementors → one task per implementor
- A test file covering many behaviors → split by the requirement IDs being tested
- An integration test that exercises a long workflow → split into setup/infrastructure task + test task

### Phase 4: Classify Dependencies

For every task, classify its relationship to every other task using these three categories:

#### Category 1: Sequential (Hard Dependency)
Task B **requires** Task A's output to exist. Task B literally cannot be written or compiled without Task A being done.

Examples:
- Implementing a repository requires the domain types it operates on
- Writing an API handler requires the service layer it calls
- Integration tests require all the components they exercise

Notation: `depends on: Task X.Y`

#### Category 2: Order-Independent (Soft Conflict)
Tasks have no logical dependency — either could be done first — but they touch shared files or shared state, so doing them concurrently would cause merge conflicts or require careful coordination.

Examples:
- Two struct implementations in the same package (both modify `mod.rs` / `lib.rs` / `__init__.py`)
- Two sets of unit tests that share a test helper file
- Two features that both add entries to a configuration struct
- Tasks that both modify `Cargo.toml` / `package.json` / `go.mod`

Notation: `conflicts with: Task X.Z` (with reason: "shared test file", "both modify mod.rs", etc.)

#### Category 3: Truly Parallel (Independent)
Tasks have no logical dependency AND no shared files. They can be assigned to different agents/developers and worked on simultaneously. The only coordination needed is at commit time — all tasks in a parallel batch must complete before committing.

Examples:
- Tasks in completely separate packages with no shared files
- A documentation task and a code task
- Two independent leaf packages that only depend on a shared core

Notation: `parallel with: Task A.B, Task C.D` (explicitly named)

### Phase 5: Organize into Execution Batches

Group tasks into **batches** — sets of tasks that can be executed together. A batch completes when ALL tasks in it are done, then the next batch can begin.

**Batch rules:**
- All tasks in a batch must have their sequential dependencies satisfied by previous batches
- Within a batch, distinguish **parallel tracks** (truly independent) from **serialized tracks** (order-independent but conflicting)
- A batch should be committable — when all tasks in a batch are done, the project should compile and all existing tests should pass

**Batch structure:**
```
Batch 1: Foundation
  Track A (serial): Task 1.1 → Task 1.2 → Task 1.3  [pkg-core types]
  Track B (serial): Task 1.4                          [test helpers]
  Tracks A and B are PARALLEL (different packages)

Batch 2: Core Services
  Track A (serial): Task 2.1 → Task 2.2  [pkg-a]
  Track B (serial): Task 2.3 → Task 2.4  [pkg-c]
  Track C (serial): Task 2.5              [pkg-a unit tests]
  Tracks A and B are PARALLEL (different packages)
  Tracks A and C CONFLICT (same package — serialize within this track)

Batch 3: Integration Layer
  Track A (serial): Task 3.1 → Task 3.2  [pkg-b, depends on pkg-a]
  (single track — no parallelization possible)
```

### Phase 6: Generate the Plan

Create `plan/{prefix}-plan.md` (or custom path from $ARGUMENTS if provided) using the template in [template.md](template.md).

**Mermaid Diagram Rules** (required for renderer compatibility — GitLab, GitHub, VS Code use older Mermaid.js):
- Always quote flowchart node labels: `A["Start here"]` not `A[Start here]`
- Always quote decision nodes: `B{"Is it ready?"}` not `B{Is it ready?}`
- Always quote subgraph titles: `subgraph sg["My Group"]` not `subgraph sg[My Group]`
- Prefer `A -- "label" --> B` link syntax over `A -->|"label"| B`
- Keep labels short — move detail into surrounding prose
- NO `<br/>` in any label or node text
- NO `<-->` bidirectional arrows — use two separate directed arrows
- NO special characters in state/flowchart labels: `()` `.` `/` `→` `__` — use plain words

The plan must include:

1. **Overview** — Project summary, total task count, batch count, estimated parallel speedup

2. **Package Dependency Graph** — Mermaid diagram of package-level dependencies (from the low-level design)

3. **Execution Batches** — Each batch with:
   - Parallel tracks clearly labeled
   - Conflict annotations within tracks
   - Commit checkpoint description

4. **Task Details** — For each task:
   - Prerequisites (sequential dependencies)
   - Conflicts (order-independent but shared files — name the shared files)
   - Parallel group (what it can run alongside)
   - Objective
   - Instructions (specific file paths, type signatures, implementation details from the low-level design)
   - Verification (what to run to confirm it works)
   - Requirements covered (FR-x.x.x IDs from the testing strategy)

5. **Task Status Tracker** — A table at the end of the plan listing every task with its status (`[ ]` not started, `[~]` in progress, `[x]` completed), prerequisites, and conflicts. This is the single source of truth for task progress — no separate tracking file.

6. **Critical Path** — The longest sequential chain through the batch graph. This is the minimum time to complete all work even with unlimited parallelism.

7. **Parallelization Summary** — Table showing which batches have parallel tracks, what the theoretical speedup is, and what the commit coordination requirements are.

8. **Requirements Traceability** — Map from FR-x.x.x to the task(s) that implement and test each requirement.

### Phase 7: Validate the Plan

Before finalizing, verify:

- [ ] Every class/struct from the low-level design's class diagrams has a task that creates it
- [ ] Every interaction from the low-level design's sequence diagrams is covered by tasks
- [ ] Every unit test from the low-level design's testing strategy appears in a task
- [ ] Every integration test from the low-level design's testing strategy appears in a task
- [ ] Every FR-x.x.x from the requirements appears in the traceability table
- [ ] No task has a circular dependency
- [ ] Every batch is committable (project compiles, tests pass after batch completes)
- [ ] Conflict annotations are specific (name the shared files, not just "same package")
- [ ] Parallel tracks within a batch are truly independent (no shared files)
- [ ] The critical path is realistic

## Output

Create `plan/{prefix}-plan.md` (create `plan/` directory if needed).

The plan should be:
- **Dependency-precise:** Every sequential dependency, soft conflict, and parallel opportunity explicitly called out
- **Batch-oriented:** Work organized into committable batches, not just a flat list
- **Traceable:** Every task links back to the low-level design and every requirement has a task
- **Honest about parallelism:** Distinguishes "can run simultaneously" from "order doesn't matter but will conflict"